Vale- Copper Cliff Mine South, Shaft Rehabilitation

Rehabilitation of a shaft from surface to 4050 level. Scope included the removal of shaft steel, piping, electrical cables and other shaft furnishings. Technica provided all skilled labour for the project including shaft personnel, hoist operators, electricians and industrial mechanics. Galloways were designed, built and installed by Technica. A temporary winch was sourced and installed.

A detailed risk assessment was completed for each task along with specific procedures complete with 3 dimensional illustrations for each step. The detailed planning that Technica completes for each project ensures the safe execution of these non-routine tasks. Please see below for illustrations of pipe, cable and steel removals.

Services provided